Provide Accurate and Timely Financial Reports.

Question

Activity 2D

Question 1:

Using the information provided in case study D, complete a financial report using the following template:

 

 

 

 

 

Activity 2D

Q1.

Project Phase Budgeted Cost Actual Cost Comments
Concrete Removal $9900 10500 The removal company underestimated the amount of concrete to be removed leading to an extra day inclusion.
Turf $3250 $3650 Due to bad weather, turf labour is increased by three days.
Planting $4755 $4345 Due to the effective work process of the planting company, the actual cost was decreased.
Paving $2140 $1930 As five m² is not required for the project actual cost was decreased.
Shade Area $6535 $6715  Due to the increment in digging work, the actual cost has increased.
Other $5625 $6075 An increase in workload has led to getting involved in more work for the project manager.