IT Project Management

Question

The purpose of this exercise is to learn how to use MS Project. It investigates how it can be used to plan out activities to enable a milestone to be achieved.

The objective of this project is to develop a plan, link the tasks, set milestones, assign a resource and cost the project.

Project Definition

  • All tasks need to be carried out in sequence
  • High Quality
  • Calculate the Cost
  • Time is fixed and the milestone can be found.

The times for the various tasks are identified below:

These times are only intended as an indication, you should be able to work them out more accurately, however use them to illustrate the plan.

 

No Tasks Duration (Mandays)
1 Write Specification 2 Days
2 Design Site 6 Days
3 Choose Web Authoring Tool 1 Day
4 Buy the package 4 Days
5 Install & Test Package 1 Day
6 Create basic Page layout 2 Days
7 Set up Colours & fonts 1 Days
8 Compose & Enter Text 3 Days
9 Customize Images 2 Days
10 Enter links 3 Days
11 Check Operation 1 Day
12 Set up ISP 5 Days
13 Publish to Web 1 Day
14 Confirm Operation 1 Day

 

Question 1 – Date when project complete is DD/MM/YYYY

 

Answer 1: 16/11/2016

Question 2 – Will be able to talk to the ISP on DD/MM/YYYY

Answer 2: 07/11/2016

Question 3 – The number of Mondays is XX

Answer3: 34 days

Question 4 – Cost for October is XXXX.XX (no currency sign)

Answer 4: 9410.00

Question 5 – Cost for November is XXXX.XX (no currency sign)

Answer 5: 5040.00

Question 6 – Total Cost for Resource is XXXXX.XX (no currency sign

Answer 6:  14450.00

Question 7 –  Month that the Computer will be purchased in

Answer 7: October

Question 8 – Total Cost of the project is XXXXX.XX (no currency sign)

Answer 8: 14450.00

Question 9 – Cost for ISP XXXXX.XX (no currency sign)

Answer 9: 0.00

 

 